  1. P

    guidance needed to parallel 2 drash gen sets together

    Could do, the PPDU can be a pricey item to get IF you can find one....that Gov controller sells on Ebay just over $100...You could check that it is not 'gooped' on the dials before you buy it and just swap it out for a new Gov controller...
  2. P

    guidance needed to parallel 2 drash gen sets together

    Oooh, they were serious about keeping you out huh? No, that is slightly different to what I described, that is the unit for low current fuel actuators...but the same dials do the same stuff. I would be real careful picking that goop off. If it is waxy and you can move it with a finger nail that...
  3. P

    guidance needed to parallel 2 drash gen sets together

    Really? Can you post a pic of the epoxy please? Right so the SYC6714 will get the two gens in phase so the breaker can be thrown to bring them together and at that point the LSM101 will take over to allow the comms cable to keep them in sysnc so they can share the load and run in parallel...
  4. P

    guidance needed to parallel 2 drash gen sets together

    When they run in parallel they should share half the load each...I am tracking what you are saying, they would each take a smaller bump as the load comes on...could be...but we can work with just 1 generator for now till you get the PPDU ... That governor controller has a couple of black...
  5. P

    guidance needed to parallel 2 drash gen sets together

    I am not saying the units cannot power the welder,I am saying that by the time it is responding to the load you are already ending the weld. Think of the gen like the cruise control on your car, when you hit a hill the speed drifts down a little till the cruise kicks it down and gives it...
  6. P

    guidance needed to parallel 2 drash gen sets together

    I think you are mixing potential power with what I am pushing at, which is the ability to respond to load change. I have a little experience with similar generators and assuming there is not a quantum difference… When a load is applied then there is a requirement for more amps which causes the...
  7. P

    guidance needed to parallel 2 drash gen sets together

    My concern would be that you would still take the same amount of time to open the fuel actuators if they are in single or parallel mode...and still get the same results.... Now if you had a way to pre-open the actuators...maybe a resistive loadbank to preload the engine then disengage that as...
  8. P

    guidance needed to parallel 2 drash gen sets together

    If you parallel the two gens you will not decrease the response time of the fuel actuators..you will likely have a bigger generator that still does not respond quickly enough...what happens with just one gen? Does it pop the main breaker? FYI, those gens use a parallel cable and a distribution...